Offcut Works

Shed and garden room planning permission checker

Answer a few questions to see whether a shed, summer house or garden room is likely to be permitted development in England, and whether it needs building regulations approval.

Where is it?
The building
m

Highest point, measured from the highest ground next to it.

m

Where the roof meets the wall.

The boundary of the whole garden, not just a fence you are next to.

The wall facing the main road is the principal elevation. This also covers the area in front of a line drawn through it to the side boundary.

A platform is raised if it is more than 0.3 metres above the ground.

The property
Building regulations
m²

How the numbers are worked out

This applies Class E, the permitted development rule for buildings in the garden of a house in England. Most garden sheds, summer houses and garden offices are permitted development, which means you do not need to apply, as long as the building stays within the limits below.

The height limits

CaseMaximum overall height
Dual-pitched roof4 m
Any other roof3 m
Any part within 2 m of the boundary of the garden2.5 m

The eaves must not be higher than 2.5 m whatever the roof. The rule about 2 metres is a height cap near the boundary. It is not a rule that a shed must be set back 2 metres.

The main conditions

Building regulations are separate

Planning permission and building regulations are different. For an outbuilding in England, the Planning Portal says building regulations will not normally apply under 15 m² with no sleeping accommodation. From 15 to 30 m² with no sleeping accommodation, approval is not normally needed if the building is at least 1 metre from every boundary or is built substantially of non-combustible materials. Anything with sleeping accommodation needs approval.

Other things to check

Questions

Can I put a shed 2 metres from the boundary?

The rule is a height cap, not a set-back. Any part within 2 metres of the garden boundary cannot be taller than 2.5 metres. You can build closer than 2 metres if the building stays under that height.

Do I need planning permission for a garden room?

Often not, if it is a single storey, within the height limits, behind the front of the house, within the 50% limit and used for something incidental to the house, such as an office or gym. Using it as a bedroom or self-contained accommodation means you need permission.

How high can a shed be without planning permission?

Up to 4 metres with a dual-pitched roof, 3 metres with any other roof, and 2.5 metres if any part is within 2 metres of the boundary of the garden. The eaves must be no higher than 2.5 metres.

Do I need building regulations for a shed?

Not normally under 15 m² with no sleeping accommodation. From 15 to 30 m² it depends on the distance to the boundary and the materials. Over 30 m² or with sleeping accommodation, it is likely to apply.

Where the defaults come from

Show the 4 sources
Defaults we could not confirm from a primary source
  • The 0.3 metre height for a raised platform comes from the government guidance and the Planning Portal. The Order itself says only "raised platform" in the part we read.
  • The government guidance we used is dated 2019. We checked Class E against the Order, which shows changes in force to 19 October 2026, and found the same limits, but we did not read every definition in it.
  • Whether an outbuilding is "incidental" is a matter of fact and degree. A council decides.
  • The Planning Portal gives no building regulations rule for outbuildings over 30 m², so the result there is a prompt to ask building control.
  • We did not cover containers for oil or gas, swimming pools, or extensions to the house.